April 2015

Purchase Leeuwenburg

Vastint Netherlands has acquired ownership of the Leeuwenburg building in Amsterdam from the seller Van der Vorm Vastgoed.

September 1, 2022

Hogeschool van Amsterdam hands over the key to Leeuwenburg

September 2022

Setting up construction site

In this phase, the construction site is set up with security cameras, construction fences, and construction buildings

October 2022

Start interior demolition phase

This phase starts with a 'soft demolition', during which the inside of the building is dismantled

November 30, 2022

Determination of zoning plan by city council

Q2 2023

Completion phase 1 - demolition phase

The demolition was successfully completed in June 2023. In total, over 5.2 million kilograms of material were dismantled, of which 97% was recycled or reused.

November 2023

Start phase 2 - interior asbestos remediation

Asbestos removal is expected to start in November 2023.

2025

Start façade dismantling phase

Part of the facade dismantling is:
• Drilling lifting holes
• Dismantling the facade with lifting chains
• Bringing down the facade elements
• Transporting all facade parts