April 2015
Purchase Leeuwenburg
Vastint Netherlands has acquired ownership of the Leeuwenburg building in Amsterdam from the seller Van der Vorm Vastgoed.
September 1, 2022
Hogeschool van Amsterdam hands over the key to Leeuwenburg
September 2022
Setting up construction site
In this phase, the construction site is set up with security cameras, construction fences, and construction buildings
October 2022
Start interior demolition phase
This phase starts with a 'soft demolition', during which the inside of the building is dismantled
November 30, 2022
Determination of zoning plan by city council
Q2 2023
Completion phase 1 - demolition phase
The demolition was successfully completed in June 2023. In total, over 5.2 million kilograms of material were dismantled, of which 97% was recycled or reused.
November 2023
Start phase 2 - interior asbestos remediation
Asbestos removal is expected to start in November 2023.
2026
Start façade dismantling phase
Part of the facade dismantling is:
• Drilling lifting holes
• Dismantling the facade with lifting chains
• Bringing down the facade elements
• Transporting all facade parts
Q2'27 – Q3'27
Phase 4: Construction
Q4'27 – Q3'28
Phase 5: Facade and Roof
Q2'28 – Q3'29
Phase 6: Structural Work
Q1'29 – Q4'29
Phase 7: Finishing
Q2'29 – Q3'29
Phase 8: ATES (Aquifer Thermal Energy Storage)
Q3'29 – Q4'29
Phase 9: Parking Garage and Logistics
Q3'29 – Q1'30